Tales of BESS #7 - Case Study: SOC discrepancy : 32MW / 32MWh (UK)

Aug. 18, 2025
2 minutes

SOC discrepancy : 32MW / 32MWh (UK)

 

 

The BESS is operated by the Technical Asset Management team of Greensolver on the behalf of the Asset owner. The BESS is 32MW / 32MWh located in UK.

As part of the TAM scope of servicesGreensolver team used on daily basis the Safety & Performance analytic tool BatteryInsight to ensure the SOC figures accuracy.

 

 

Wrong SOC figures given by the BMS and used by the RTM operator led to operational discrepancies and imbalances for the WM position and DFR serviceswhich end by lost of revenues.

Thanks to the raw data: Temperature, Voltage and Current given by the SCADA/BMS at Battery racks level, Greensolver team was able to highlight SOC deviation between the SOC figures given by the BMS on site and the SOC figures calculated by BatteryInsight.

 

 

As part of the Performance feature of the tool, recurrent SOC deviation alarms was triggered, highlighting potential SOC calculation issue by the BMS from commissioning date. Below summary of the action plan managed by Greensolver team:

  • First action: by tracking those alarms, Greensolver team could focus cause on the BMS
  • Second actionGreensolver team requested remedial action to the Battery OEM
  • Third actionBattery OEM performed a software update of the BMS to improve the SOC calculation

 

 

From the date of the software updateno more critical SOC deviation alarm have been raised. RTM operator gained in visibility to position the asset on the market applications reducing the risk of discrepancy.

Graph asset output
Écart graphique SOC

Written by David Roissé

Blog

The Latest Renewable Energy News

Greensolver will be at 27th Annual Submit of French Renewable Energy Trade Association – 29th of September

Greensolver will be at Solar and Storage Birmingham – 22-24 of September

Greensolver will present at the INES Solar Conference on September 15

Greensolver will be at European Power Investment Summit 2026 – 16st of September

Greensolver at the Onshore Wind Conference 2026 – 1st of September

AMPYR Distributed Energy: Technical Asset Management of a 70 MW pan-European solar portfolio

Webinar Replay – Modeling the Economic Potential of BESS: How to Manage Uncertainty | June 17, 2:00 p.m. CET

Greensolver will be attending the 12th GreenUnivers Infrastructure Financing Conference on July 1

Greensolver at the National Event on “Flexibility in Renewable Energy and Storage” — July 2

Resources and insights Tales of BESS #7 – Case Study: SOC discrepancy : 32MW / 32MWh (UK)