battery energy storage system with solar panels and wind turbines behind battery energy storage system with solar panels and wind turbines behind
Bess

Tales of BESS #5 - Case Study: Safety & Performance Analysis under TAM contract

Jul. 18, 2025
1 minute

Safety & Performance Analysis under TAM contract: 32MW / 32MWh (UK)

 

 

The BESS is operated by the Technical Asset Management team of Greensolver on the behalf of the Asset owner. The BESS is 32MW / 32MWh located in UK.

As part of the TAM scope of services, Greensolver team led an analysis to check Safety & Performance status of the plant, throughout a 8 months operational period.

Greensolver team conducted the analysis with the support of an Analytic tool provided by a third-party partner.

 

 

Thanks to the raw data: Temperature, Voltage and Current given by the SCADA at Battery rack level, Greensolver was able to analyse :

  • State-of-Safety: by tracking over-voltage / over-temperature / cell imbalance to prevent Thermal Runaway
  • Performance: by checking estimation and accuracy of SOC and SOH / BMS faults
  • Lifetime: by checking operational condition vs battery OEM requirements (temperature, C-Rate)

 

 

This Safety & Performance analysis allowed to highlight issues, which have been then raised to the battery OEM :

  • State-of-Safety: frequent cell imbalance caused by weak cells, which could then lead to over-voltage and over-charge in the Battery cells and at the end Thermal Runaway
  • Performance: remaining useful capacity (SOH) below the warranty of the battery OEM / frequent faulty measurement of the BMS, leading to SOC deviation (wrong voltage measurement)
  • Lifetime: higher temperature of the battery module than recommended, which could accelerate the ageing
Illustration of rack voltages wrong monitoring
Rest conditions graph

Written by David Roissé

Blog

The Latest Renewable Energy News

Greensolver at the Solar and Storage Paris – 14-15 October 2026

Greensolver at the Battery Asset Management Summit UK & Ireland – 13-14 October 2026

Press Release – Marie Bartle Joins Greensolver as BESS Director

Marie Bartle Joins Greensolver as BESS Director

Wind farm performance: why standard monitoring often misses the real picture

Greensolver will be at 27th Annual Submit of French Renewable Energy Trade Association – 29th of September

Greensolver will be at Solar and Storage Birmingham – 22-24 of September

Greensolver will present at the INES Solar Conference on September 15

Greensolver will be at European Power Investment Summit 2026 – 16st of September

Resources and insights Tales of BESS #5 – Case Study: Safety & Performance Analysis under TAM contract