Tales of BESS #5 - Case Study: Safety & Performance Analysis under TAM contract

Jul. 18, 2025
1 minute

Safety & Performance Analysis under TAM contract: 32MW / 32MWh (UK)

 

 

The BESS is operated by the Technical Asset Management team of Greensolver on the behalf of the Asset owner. The BESS is 32MW / 32MWh located in UK.

As part of the TAM scope of servicesGreensolver team led an analysis to check Safety & Performance status of the plant, throughout a 8 months operational period.

Greensolver team conducted the analysis with the support of an Analytic tool provided by a third-party partner.

 

 

Thanks to the raw data: Temperature, Voltage and Current given by the SCADA at Battery rack level, Greensolver was able to analyse :

  • State-of-Safety: by tracking over-voltage / over-temperature / cell imbalance to prevent Thermal Runaway
  • Performance: by checking estimation and accuracy of SOC and SOH / BMS faults
  • Lifetime: by checking operational condition vs battery OEM requirements (temperature, C-Rate)

 

 

This Safety & Performance analysis allowed to highlight issues, which have been then raised to the battery OEM :

  • State-of-Safetyfrequent cell imbalance caused by weak cells, which could then lead to over-voltage and over-charge in the Battery cells and at the end Thermal Runaway
  • Performanceremaining useful capacity (SOH) below the warranty of the battery OEM / frequent faulty measurement of the BMS, leading to SOC deviation (wrong voltage measurement)
  • Lifetime: higher temperature of the battery module than recommended, which could accelerate the ageing
Illustration of rack voltages wrong monitoring
Rest conditions graph

Written by David Roissé

Blog

The Latest Renewable Energy News

Greensolver at the UK Solar Summit — London, 30th of June 2026

Greensolver at Intersolar Europe — Munich, 23-25th June 2026

Webinar — How to Manage Uncertainty in BESS | 17 June, 2 p

Greensolver at the Régate EnR — On board the Lucille Experience, Montpellier, 17–18 June

Greensolver at the Colloque National Photovoltaïque — Strasbourg, 9th June

Greensolver at Inspiratia Datacentres: Power, Risk & Resilience — London, 18 June

Case Study 2 – Portfolio of 10 projects -15MW AgriPV Technical Due Diligence for Bank Financing

Greensolver will be at Solarplaza France – June 3rd

Solar panels with a human and its tablet and helmet

Case Study : Estimated Yield Assessment for Complex AgriPV Systems

Resources and insights Tales of BESS #5 – Case Study: Safety & Performance Analysis under TAM contract