Pre-planning permission application submission Review: 100MW / 100MWh (UK)

 

 

The client was looking for an independent third party to review a  100MW/100MWh BESS asset’s general layout and design before pre-planning application to identify any key design flaws/red flags and discuss findings.

Greensolver team reviewed the planning drawings, the flood risk assessment, the noise impact assessment and the fire risk management strategy.

 

 

Greensolver team well conducted the analysis by flagging key things to anticipate before planning application, as :

General Layout :

  • Land area : ensure compatible activity presence around the site
  • Access : ensure efficient access during Construction phase (trucks and construction equipment) and during Operation phase (fire safety services, O&M provider vehicle )
  • Internal circulation : ensure operational efficiency safety and manutention
  • Noise mitigation : ensure noise level mitigation
  • Vegetation management : ensure consistency between regulation (National Plant Specification) and operation

Flood Risk :

  • Compatibility of the equipment Layout with the Local Flood Risk Assessment
  • Consistency of the Drainage equipment to be installed

Fire Risk : as per Standards (NFPA855) and battery OEM requirements

  • Procedure : ensure Safety of personnel and equipment
  • Equipment design : ensure Detection and Suppression
  • Site layout : mitigation of Fire Spread and efficient evacuation
Battery energy storage system map

Written by David Roissé

Blog

The Latest Renewable Energy News

Greensolver will be at 27th Annual Submit of French Renewable Energy Trade Association – 29th of September

Greensolver will be at Solar and Storage Birmingham – 22-24 of September

Greensolver will present at the INES Solar Conference on September 15

Greensolver will be at European Power Investment Summit 2026 – 16st of September

Greensolver at the Onshore Wind Conference 2026 – 1st of September

AMPYR Distributed Energy: Technical Asset Management of a 70 MW pan-European solar portfolio

Webinar Replay – Modeling the Economic Potential of BESS: How to Manage Uncertainty | June 17, 2:00 p.m. CET

Greensolver will be attending the 12th GreenUnivers Infrastructure Financing Conference on July 1

Greensolver at the National Event on “Flexibility in Renewable Energy and Storage” — July 2

Resources and insights Tales of BESS #3 – Case Study: Pre-planning permission application submission review