Battery energy storage open with cables Battery energy storage open with cables
Bess

Tales of BESS #11 - Case study: Technical Due Diligence for BESS project: 17.75MW / 35.5MWh (FR) 

Oct. 2, 2025
2 minutes

Tales of BESS #11 – Case study: Technical Due Diligence for BESS project: 17.75MW / 35.5MWh (FR)

Technical Due Diligence for BESS project: 17.75MW / 35.5MWh (FR) 

 

 

Greensolver performed the technical due diligence for a standalone BESS asset underdevelopment in France 17.75MW/35.5MWh.

The scope of the work covered:

  • Regulatory:
    • Review of ICPE requirements and tracking of its development
    • Application of evolving regulatory requirements to technical specifications

 

 

  • Technical:
    • Review of CATL’s BESS Model: EnerOne+
    • Site Assessment and Review of the proposed layout
    • Design review and capacity to operate on primary reserve markets
    • Contracts review (Warranty, EPC, and O&M)
    • Augmentation Strategy Evaluation
    • Review of compliance with evolving regulatory requirements

 

 

Through the review of the regulatory requirements and their anticipated changes, the technical capabilities of the BESS project were optimized to ensure compliance and mitigate potential risks. Such work was ensured by advising the owner to:

  • Acquisition of rights to neighboring land to facilitate regulatory developments
  • Amend site layout to ensure safety
  • Consideration of additional sub-systems
  • Negotiation of improved terms for the warranty and O&M terms

 

 

Written by Nikko Talplacido
Blog

The Latest Renewable Energy News

Greensolver is the New Member of the UK’s Energy Storage Network

Press Release – Greensolver partners with Aevy to enhance asset management through AI-powered document intelligence

PRESS RELEASE – Greensolver partners with Tipspeed to strengthen wind farm performance services

Battery Energy Storage Systems with solar panels next to it

Greensolver will be in London for the Solar and Storage Live – April 29th

Wind farm with sunset

Greensolver will participate in the WindEurope 2026 in Madrid – April 21st

Battery Energy Storage Systems in a field with sunrising

Reshaping France’s Renewable Energy Market: The Role of BESS under PPE 3

Construction of solar panels with humans dressed for construction

Updates on Technical and Commercial Asset Management service in 2026

People smiling at corporate event

Greensolver will participate in the Energyear 2026 in Madrid – March 24 & 25

Solar panels in line

Design Choices That Define Lifetime Performance

Resources and insights Tales of BESS #11 – Case study: Technical Due Diligence for BESS project: 17.75MW / 35.5MWh (FR)