Technical Due Diligence for BESS project: 17.75MW / 35.5MWh (FR) 

 

 

Greensolver performed the technical due diligence for a standalone BESS asset underdevelopment in France 17.75MW/35.5MWh.

The scope of the work covered:

  • Regulatory:
    • Review of ICPE requirements and tracking of its development
    • Application of evolving regulatory requirements to technical specifications

 

 

  • Technical:
    • Review of CATL’s BESS Model: EnerOne+
    • Site Assessment and Review of the proposed layout
    • Design review and capacity to operate on primary reserve markets
    • Contracts review (Warranty, EPC, and O&M)
    • Augmentation Strategy Evaluation
    • Review of compliance with evolving regulatory requirements

 

 

Through the review of the regulatory requirements and their anticipated changes, the technical capabilities of the BESS project were optimized to ensure compliance and mitigate potential risks. Such work was ensured by advising the owner to:

  • Acquisition of rights to neighboring land to facilitate regulatory developments
  • Amend site layout to ensure safety
  • Consideration of additional sub-systems
  • Negotiation of improved terms for the warranty and O&M terms

 

 

Written by Nikko Talplacido
Blog

The Latest Renewable Energy News

Webinar Replay – Modeling the Economic Potential of BESS: How to Manage Uncertainty | June 17, 2:00 p.m. CET

Greensolver will be attending the 12th GreenUnivers Infrastructure Financing Conference on July 1

Greensolver at the National Event on “Flexibility in Renewable Energy and Storage” — July 2

Greensolver at the Wind Power Finance & Investment Summit 2026 – London, 1st of July

Compliance Monitoring at GW Scale: Why the Best Large Operators Get Better, Not Busier

Aerial view of solar panels lined up in a field

Greensolver at the UK Solar Summit — London, 30th of June 2026

Talks with people eating and drinking in front of the stands

Greensolver at Intersolar Europe — Munich, 23-25th June 2026

Plant in front of a computer showing a webinar presentation

Webinar — How to Manage Uncertainty in BESS | 17 June, 2 p

People in a boat looking at the camera and waving hands

Greensolver at the Régate EnR — On board the Lucille Experience, Montpellier, 17–18 June

Resources and insights Tales of BESS #11 – Case study: Technical Due Diligence for BESS project: 17.75MW / 35.5MWh (FR)