Tales of BESS #10 - Case study: Technical Due Diligence on two Greek BESS projects: Totaling 100MW / 200MWh (GRC) 

Oct. 2, 2025
2 minutes

Tales of BESS #10 – Case study: Technical Due Diligence on two Greek BESS projects: Totaling 100MW / 200MWh (GRC)

Technical Due Diligence on two Greek BESS projects: Totaling 100MW / 200MWh (GRC)

 

 

As the Lender Technical Advisor, Greensolver conducted Technical Due Diligence for two standalone BESS assets 50MW/100MWh in the context of the project’s financing.

The scope of the work covered:

  • Regulatory:
    • Review of grant requirements and tracking of its development
    • Application of evolving regulatory requirements to technical specifications and financial model

 

 

  • Technical:
    • Review of CATL’s BESS (Model: EnerC+)
    • Review of the permits and licenses
    • Site Assessment and Review of the proposed layout
    • Design review and capacity to operate on primary reserve markets
    • Contracts review (Supply Agreement, EPC, and O&M)
    • Augmentation Strategy Evaluation
    • Review of grant compliance

 

 

  • Financial:
    • Review of the financial model, validating assumptions and proposing suitable parameters where required CAPEX, OPEX, budgets, revenues)
    • Review of grant compliance

 

 

Through the Greensolver’s audit of the project, the proposed system was found to be aligned with industry standards. Minor risk from the selected site was identified, with mitigation investigated and proposed. The Financial Model was found to require revision and was therefore updated to better reflect local conditions.

 

 

Written by Nikko Talplacido
Blog

The Latest Renewable Energy News

Greensolver is the New Member of the UK’s Energy Storage Network

Press Release – Greensolver partners with Aevy to enhance asset management through AI-powered document intelligence

PRESS RELEASE – Greensolver partners with Tipspeed to strengthen wind farm performance services

Battery Energy Storage Systems with solar panels next to it

Greensolver will be in London for the Solar and Storage Live – April 29th

Wind farm with sunset

Greensolver will participate in the WindEurope 2026 in Madrid – April 21st

Battery Energy Storage Systems in a field with sunrising

Reshaping France’s Renewable Energy Market: The Role of BESS under PPE 3

Construction of solar panels with humans dressed for construction

Updates on Technical and Commercial Asset Management service in 2026

People smiling at corporate event

Greensolver will participate in the Energyear 2026 in Madrid – March 24 & 25

Solar panels in line

Design Choices That Define Lifetime Performance

Resources and insights Tales of BESS #10 – Case study: Technical Due Diligence on two Greek BESS projects: Totaling 100MW / 200MWh (GRC)