Tales of BESS #10 - Case study: Technical Due Diligence on two Greek BESS projects: Totaling 100MW / 200MWh (GRC) 

Oct. 2, 2025
2 minutes

Tales of BESS #10 – Case study: Technical Due Diligence on two Greek BESS projects: Totaling 100MW / 200MWh (GRC)

Technical Due Diligence on two Greek BESS projects: Totaling 100MW / 200MWh (GRC)

 

 

As the Lender Technical Advisor, Greensolver conducted Technical Due Diligence for two standalone BESS assets 50MW/100MWh in the context of the project’s financing.

The scope of the work covered:

  • Regulatory:
    • Review of grant requirements and tracking of its development
    • Application of evolving regulatory requirements to technical specifications and financial model

 

 

  • Technical:
    • Review of CATL’s BESS (Model: EnerC+)
    • Review of the permits and licenses
    • Site Assessment and Review of the proposed layout
    • Design review and capacity to operate on primary reserve markets
    • Contracts review (Supply Agreement, EPC, and O&M)
    • Augmentation Strategy Evaluation
    • Review of grant compliance

 

 

  • Financial:
    • Review of the financial model, validating assumptions and proposing suitable parameters where required CAPEX, OPEX, budgets, revenues)
    • Review of grant compliance

 

 

Through the Greensolver’s audit of the project, the proposed system was found to be aligned with industry standards. Minor risk from the selected site was identified, with mitigation investigated and proposed. The Financial Model was found to require revision and was therefore updated to better reflect local conditions.

 

 

Written by Nikko Talplacido
Blog

The Latest Renewable Energy News

Greensolver will be at 27th Annual Submit of French Renewable Energy Trade Association – 29th of September

Greensolver will be at Solar and Storage Birmingham – 22-24 of September

Greensolver will present at the INES Solar Conference on September 15

Greensolver will be at European Power Investment Summit 2026 – 16st of September

Greensolver at the Onshore Wind Conference 2026 – 1st of September

AMPYR Distributed Energy: Technical Asset Management of a 70 MW pan-European solar portfolio

Webinar Replay – Modeling the Economic Potential of BESS: How to Manage Uncertainty | June 17, 2:00 p.m. CET

Greensolver will be attending the 12th GreenUnivers Infrastructure Financing Conference on July 1

Greensolver at the National Event on “Flexibility in Renewable Energy and Storage” — July 2

Resources and insights Tales of BESS #10 – Case study: Technical Due Diligence on two Greek BESS projects: Totaling 100MW / 200MWh (GRC)