Tales of BESS #10 - Case study: Technical Due Diligence on two Greek BESS projects: Totaling 100MW / 200MWh (GRC) 

Oct. 2, 2025
2 minutes

Tales of BESS #10 – Case study: Technical Due Diligence on two Greek BESS projects: Totaling 100MW / 200MWh (GRC)

Technical Due Diligence on two Greek BESS projects: Totaling 100MW / 200MWh (GRC)

 

 

As the Lender Technical Advisor, Greensolver conducted Technical Due Diligence for two standalone BESS assets 50MW/100MWh in the context of the project’s financing.

The scope of the work covered:

  • Regulatory:
    • Review of grant requirements and tracking of its development
    • Application of evolving regulatory requirements to technical specifications and financial model

 

 

  • Technical:
    • Review of CATL’s BESS (Model: EnerC+)
    • Review of the permits and licenses
    • Site Assessment and Review of the proposed layout
    • Design review and capacity to operate on primary reserve markets
    • Contracts review (Supply Agreement, EPC, and O&M)
    • Augmentation Strategy Evaluation
    • Review of grant compliance

 

 

  • Financial:
    • Review of the financial model, validating assumptions and proposing suitable parameters where required CAPEX, OPEX, budgets, revenues)
    • Review of grant compliance

 

 

Through the Greensolver’s audit of the project, the proposed system was found to be aligned with industry standards. Minor risk from the selected site was identified, with mitigation investigated and proposed. The Financial Model was found to require revision and was therefore updated to better reflect local conditions.

 

 

Written by Nikko Talplacido
Blog

The Latest Renewable Energy News

Phone with stats

Why the Portfolio Effect Is a Game-Changer in Solar Investment

Protected: Wind Turbine Maintenance: A Guide for Asset Owners and Investors

Picture of Paris from above with the Eiffel Tower

Greensolver at the Solar and Storage Paris – 14-15 October 2026

Big Ben in London with sunset

Greensolver at the Battery Asset Management Summit UK & Ireland – 13-14 October 2026

Picture of Marie Bartle

Press Release – Marie Bartle Joins Greensolver as BESS Director

Presentation of a new colleague

Marie Bartle Joins Greensolver as BESS Director

Wind Turbine in the middle of clouds

Wind farm performance: why standard monitoring often misses the real picture

Concert room with many people

Greensolver will be at 27th Annual Submit of French Renewable Energy Trade Association – 29th of September

Weeding room with people getting married

Greensolver will be at Solar and Storage Birmingham – 22-24 of September

Resources and insights Tales of BESS #10 – Case study: Technical Due Diligence on two Greek BESS projects: Totaling 100MW / 200MWh (GRC)