Case Study 2 - Portfolio of 10 projects -15MW AgriPV Technical Due Diligence for Bank Financing

Apr. 28, 2026
5 minutes

The bank requested a customized P50 and P90 modeling for the Agri-PV projects, incorporating the unique characteristics of farming seasons to ensure accurate and reliable long-term financial projections.

 

 

Greensolver conducted a technical due diligence tailored to Agri-PV projects, considering:

  • Plantation characteristics (height, growth period, and need for anti-tracking to optimize plant growth).
  • Tracker control modeling to allow maintenance equipment or livestock passage.
  • Multiple simulations to accommodate various scenarios.
  • Environmental analysis to identify constraints, risks, and success factors.
  • Financial model, equipment, and plant design review, integrating phenological calendars for agricultural seasonality.

 

 

 

Thanks to Greensolver’s expertise, the client secured the Bank’s financing, enabling the project to operate at optimal performance with long-term reliability.

  • 14,6 MWc installed
  • 16,3 GWh of production

Greensolver’s track records Agri PV.

 

 

More than 70% of the PV projects we work on can be considered Agri-PV, with varying degrees of complexity. By extrapolation, we estimate that we have audited more than 10 GW of Agri-PV projects (1000+ projects) out of a total of 35 GW of PV due diligence.

Total in 2025: 211 projects (2GW) with a majority of complex agri PV projects.

Written by Antonin Lagrue

 

Greensolver’s key solar references.

Out of the 55 GW of technical due diligence we have conducted, here is a selection of solar due diligence projects where we acted as technical auditors :

Want to meet our solar advisors?

Schedule a meeting here Schedule a meeting here
Blog

The Latest Renewable Energy News

Phone with stats

Why the Portfolio Effect Is a Game-Changer in Solar Investment

Protected: Wind Turbine Maintenance: A Guide for Asset Owners and Investors

Picture of Paris from above with the Eiffel Tower

Greensolver at the Solar and Storage Paris – 14-15 October 2026

Big Ben in London with sunset

Greensolver at the Battery Asset Management Summit UK & Ireland – 13-14 October 2026

Picture of Marie Bartle

Press Release – Marie Bartle Joins Greensolver as BESS Director

Presentation of a new colleague

Marie Bartle Joins Greensolver as BESS Director

Wind Turbine in the middle of clouds

Wind farm performance: why standard monitoring often misses the real picture

Concert room with many people

Greensolver will be at 27th Annual Submit of French Renewable Energy Trade Association – 29th of September

Weeding room with people getting married

Greensolver will be at Solar and Storage Birmingham – 22-24 of September

Resources and insights Case Study 2 – Portfolio of 10 projects -15MW AgriPV Technical Due Diligence for Bank Financing