Tales of BESS #3 - Case Study: Pre-planning permission application submission review

Jul. 18, 2025
1 minute

Pre-planning permission application submission Review: 100MW / 100MWh (UK)

 

 

The client was looking for an independent third party to review a  100MW/100MWh BESS asset’s general layout and design before pre-planning application to identify any key design flaws/red flags and discuss findings.

Greensolver team reviewed the planning drawings, the flood risk assessment, the noise impact assessment and the fire risk management strategy.

 

 

Greensolver team well conducted the analysis by flagging key things to anticipate before planning application, as :

General Layout :

  • Land area : ensure compatible activity presence around the site
  • Access : ensure efficient access during Construction phase (trucks and construction equipment) and during Operation phase (fire safety services, O&M provider vehicle )
  • Internal circulation : ensure operational efficiency safety and manutention
  • Noise mitigation : ensure noise level mitigation
  • Vegetation management : ensure consistency between regulation (National Plant Specification) and operation

Flood Risk :

  • Compatibility of the equipment Layout with the Local Flood Risk Assessment
  • Consistency of the Drainage equipment to be installed

Fire Risk : as per Standards (NFPA855) and battery OEM requirements

  • Procedure : ensure Safety of personnel and equipment
  • Equipment design : ensure Detection and Suppression
  • Site layout : mitigation of Fire Spread and efficient evacuation
Battery energy storage system map

Written by David Roissé

Blog

The Latest Renewable Energy News

Phone with stats

Why the Portfolio Effect Is a Game-Changer in Solar Investment

Protected: Wind Turbine Maintenance: A Guide for Asset Owners and Investors

Tales of Wind Series Illustrations

Tales of Wind – Complete Series

Picture of Paris from above with the Eiffel Tower

Greensolver at the Solar and Storage Paris – 14-15 October 2026

Big Ben in London with sunset

Greensolver at the Battery Asset Management Summit UK & Ireland – 13-14 October 2026

Picture of Marie Bartle

Press Release – Marie Bartle Joins Greensolver as BESS Director

Presentation of a new colleague

Marie Bartle Joins Greensolver as BESS Director

Wind Turbine in the middle of clouds

Wind farm performance: why standard monitoring often misses the real picture

Concert room with many people

Greensolver will be at 27th Annual Submit of French Renewable Energy Trade Association – 29th of September

Resources and insights Tales of BESS #3 – Case Study: Pre-planning permission application submission review