Tales of BESS #11 - Case study: Technical Due Diligence for BESS project: 17.75MW / 35.5MWh (FR) 

Oct. 2, 2025
2 minutes

Tales of BESS #11 – Case study: Technical Due Diligence for BESS project: 17.75MW / 35.5MWh (FR)

Technical Due Diligence for BESS project: 17.75MW / 35.5MWh (FR) 

 

 

Greensolver performed the technical due diligence for a standalone BESS asset underdevelopment in France 17.75MW/35.5MWh.

The scope of the work covered:

  • Regulatory:
    • Review of ICPE requirements and tracking of its development
    • Application of evolving regulatory requirements to technical specifications

 

 

  • Technical:
    • Review of CATL’s BESS Model: EnerOne+
    • Site Assessment and Review of the proposed layout
    • Design review and capacity to operate on primary reserve markets
    • Contracts review (Warranty, EPC, and O&M)
    • Augmentation Strategy Evaluation
    • Review of compliance with evolving regulatory requirements

 

 

Through the review of the regulatory requirements and their anticipated changes, the technical capabilities of the BESS project were optimized to ensure compliance and mitigate potential risks. Such work was ensured by advising the owner to:

  • Acquisition of rights to neighboring land to facilitate regulatory developments
  • Amend site layout to ensure safety
  • Consideration of additional sub-systems
  • Negotiation of improved terms for the warranty and O&M terms

 

 

Written by Nikko Talplacido
Blog

The Latest Renewable Energy News

Phone with stats

Why the Portfolio Effect Is a Game-Changer in Solar Investment

Protected: Wind Turbine Maintenance: A Guide for Asset Owners and Investors

Picture of Paris from above with the Eiffel Tower

Greensolver at the Solar and Storage Paris – 14-15 October 2026

Big Ben in London with sunset

Greensolver at the Battery Asset Management Summit UK & Ireland – 13-14 October 2026

Picture of Marie Bartle

Press Release – Marie Bartle Joins Greensolver as BESS Director

Presentation of a new colleague

Marie Bartle Joins Greensolver as BESS Director

Wind Turbine in the middle of clouds

Wind farm performance: why standard monitoring often misses the real picture

Concert room with many people

Greensolver will be at 27th Annual Submit of French Renewable Energy Trade Association – 29th of September

Weeding room with people getting married

Greensolver will be at Solar and Storage Birmingham – 22-24 of September

Resources and insights Tales of BESS #11 – Case study: Technical Due Diligence for BESS project: 17.75MW / 35.5MWh (FR)