Tales of BESS #5 - Case Study: Safety & Performance Analysis under TAM contract

Jul. 18, 2025
1 minute

Safety & Performance Analysis under TAM contract: 32MW / 32MWh (UK)

 

 

The BESS is operated by the Technical Asset Management team of Greensolver on the behalf of the Asset owner. The BESS is 32MW / 32MWh located in UK.

As part of the TAM scope of servicesGreensolver team led an analysis to check Safety & Performance status of the plant, throughout a 8 months operational period.

Greensolver team conducted the analysis with the support of an Analytic tool provided by a third-party partner.

 

 

Thanks to the raw data: Temperature, Voltage and Current given by the SCADA at Battery rack level, Greensolver was able to analyse :

  • State-of-Safety: by tracking over-voltage / over-temperature / cell imbalance to prevent Thermal Runaway
  • Performance: by checking estimation and accuracy of SOC and SOH / BMS faults
  • Lifetime: by checking operational condition vs battery OEM requirements (temperature, C-Rate)

 

 

This Safety & Performance analysis allowed to highlight issues, which have been then raised to the battery OEM :

  • State-of-Safetyfrequent cell imbalance caused by weak cells, which could then lead to over-voltage and over-charge in the Battery cells and at the end Thermal Runaway
  • Performanceremaining useful capacity (SOH) below the warranty of the battery OEM / frequent faulty measurement of the BMS, leading to SOC deviation (wrong voltage measurement)
  • Lifetime: higher temperature of the battery module than recommended, which could accelerate the ageing
Illustration of rack voltages wrong monitoring
Rest conditions graph

Written by David Roissé

Blog

The Latest Renewable Energy News

Greensolver will participate in the Energyear 2026 in Madrid – March 24 & 25

Solar panels in line

Design Choices That Define Lifetime Performance

How to Build Reliable BESS Projects in Greece?

Conference energyear 2025

Greensolver will participate in the Energy Storage Summit 2026 in London – February 24 & 25

Data Centers and Renewable Energy in Europe: The Symbiosis Redefining Investment

Greensolver unveils a new brand identity and website to better serve renewable energy stakeholders

PRESS RELEASE – Greensolver Reinvents Its Brand Identity to Deliver Technical and Financial Value

Spain’s Renewable Energy Landscape 2026 : Opportunities and Challenges

Women clapping in an office

Greensolver will be in the 2nd Flexibility and Storage Event by GreenUnivers – 5th of february

Resources and insights Tales of BESS #5 – Case Study: Safety & Performance Analysis under TAM contract