As the Lender Technical Advisor, Greensolver conducted Technical Due Diligence for two standalone BESS assets 100MW/200MWh in the context of the project’s financing.

The scope of the work covered:

  • Regulatory:
    • Review of grant requirements and tracking of its development
    • Application of evolving regulatory requirements to technical specifications and financial model
  • Technical:
    • Review of Narada’s BESS
    • Review of the permits and licenses
    • Site Assessment and Review of the proposed layout
    • Design review and capacity to operate on primary reserve markets
    • Contracts review (Supply Agreement, EPC, O&M, LTSA, and Aggregation)
    • Augmentation Strategy Evaluation
    • Review of grant compliance
  • Financial:
    • Review of the financial model, validating assumptions and proposing suitable parameters where required CAPEX, OPEX, budgets, revenues)
    • Review of grant compliance

Through the Greensolver’s audit of the project, the technical review resulted in:

  • Site layout and system design revision, ensuring regulatory and grant compliance
  • Financial Model parameters revision, reflecting realistic-world conditions and up-to-date market information.
Battery Energy Storage System
Written by Nikko Talplacido
Blog

The Latest Renewable Energy News

Solar panels in line

Design Choices That Define Lifetime Performance

How to Build Reliable BESS Projects in Greece?

Conference energyear 2025

Greensolver will participate in the Energy Storage Summit 2026 in London – February 24 & 25

Data Centers and Renewable Energy in Europe: The Symbiosis Redefining Investment

Greensolver unveils a new brand identity and website to better serve renewable energy stakeholders

PRESS RELEASE – Greensolver Reinvents Its Brand Identity to Deliver Technical and Financial Value

Spain’s Renewable Energy Landscape 2026 : Opportunities and Challenges

Women clapping in an office

Greensolver will be in the 2nd Flexibility and Storage Event by GreenUnivers – 5th of february

Solar panels with sheeps around like agri-pv

Agrivoltaics – Dual Land Use, New Incentives, and Market Opportunities

Resources and insights Tales of BESS #9 – Case study: Technical Due Diligence on two Greek BESS projects: Totaling 200MW / 400MWh (GRC)