Tales of BESS #9 - Case study: Technical Due Diligence on two Greek BESS projects: Totaling 200MW / 400MWh (GRC)

Sep. 23, 2025
1 minute

As the Lender Technical Advisor, Greensolver conducted Technical Due Diligence for two standalone BESS assets 100MW/200MWh in the context of the project’s financing.

The scope of the work covered:

  • Regulatory:
    • Review of grant requirements and tracking of its development
    • Application of evolving regulatory requirements to technical specifications and financial model
  • Technical:
    • Review of Narada’s BESS
    • Review of the permits and licenses
    • Site Assessment and Review of the proposed layout
    • Design review and capacity to operate on primary reserve markets
    • Contracts review (Supply Agreement, EPC, O&M, LTSA, and Aggregation)
    • Augmentation Strategy Evaluation
    • Review of grant compliance
  • Financial:
    • Review of the financial model, validating assumptions and proposing suitable parameters where required CAPEX, OPEX, budgets, revenues)
    • Review of grant compliance

Through the Greensolver’s audit of the project, the technical review resulted in:

  • Site layout and system design revision, ensuring regulatory and grant compliance
  • Financial Model parameters revision, reflecting realistic-world conditions and up-to-date market information.
Battery Energy Storage System
Written by Nikko Talplacido
Blog

The Latest Renewable Energy News

Solar panels with sheeps around like agri-pv

Agrivoltaics – Dual Land Use, New Incentives, and Market Opportunities

Handshaking by two women

Why will certifications become necessary in 2026?

Solar Panel with Blue sky

Grid Availability and Curtailment: The Hidden Drivers of Solar Asset Performance

Sun with ondulations in purple

Smart Coexistence: When Sheep, Solar, and AI Work Together

Team of people at a conference

Greensolver will be in Montpellier for Energaia – 10 of december

Battery energy storage open

What the Update to NFPA 855 Means for Energy Storage Safety ?

Battery energy storage open with cables

Tales of BESS #11 – Case study: Technical Due Diligence for BESS project: 17.75MW / 35.5MWh (FR) 

Battery energy storage contener

Tales of BESS #10 – Case study: Technical Due Diligence on two Greek BESS projects: Totaling 100MW / 200MWh (GRC) 

Solar farm with solar panels with grass

Safety Concerns in Single-Axis Tracker PV Plants: Risks and Mitigation Strategies

Resources and insights Tales of BESS #9 – Case study: Technical Due Diligence on two Greek BESS projects: Totaling 200MW / 400MWh (GRC)