battery energy storage system with solar panels and wind turbines behind battery energy storage system with solar panels and wind turbines behind
Bess

Tales of BESS #7 - Case Study: SOC discrepancy : 32MW / 32MWh (UK)

Aug. 18, 2025
2 minutes

SOC discrepancy : 32MW / 32MWh (UK)

The BESS is operated by the Technical Asset Management team of Greensolver on the behalf of the Asset owner. The BESS is 32MW / 32MWh located in UK.

As part of the TAM scope of servicesGreensolver team used on daily basis the Safety & Performance analytic tool BatteryInsight to ensure the SOC figures accuracy.

Wrong SOC figures given by the BMS and used by the RTM operator led to operational discrepancies and imbalances for the WM position and DFR serviceswhich end by lost of revenues.

Thanks to the raw data: Temperature, Voltage and Current given by the SCADA/BMS at Battery racks level, Greensolver team was able to highlight SOC deviation between the SOC figures given by the BMS on site and the SOC figures calculated by BatteryInsight.

As part of the Performance feature of the tool, recurrent SOC deviation alarms was triggered, highlighting potential SOC calculation issue by the BMS from commissioning date. Below summary of the action plan managed by Greensolver team:

  • First action: by tracking those alarms, Greensolver team could focus cause on the BMS
  • Second actionGreensolver team requested remedial action to the Battery OEM
  • Third actionBattery OEM performed a software update of the BMS to improve the SOC calculation

From the date of the software updateno more critical SOC deviation alarm have been raised. RTM operator gained in visibility to position the asset on the market applications reducing the risk of discrepancy.

Graph asset output
Écart graphique SOC

Written by David Roissé

Blog

The Latest Renewable Energy News

Handshaking by two women

Why will certifications become necessary in 2026?

Solar Panel with Blue sky

Grid Availability and Curtailment: The Hidden Drivers of Solar Asset Performance

Sun with ondulations in purple

Smart Coexistence: When Sheep, Solar, and AI Work Together

Team of people at a conference

Greensolver will be in Montpellier for Energaia – 10 of december

Battery energy storage open

What the Update to NFPA 855 Means for Energy Storage Safety ?

Battery energy storage open with cables

Tales of BESS #11 – Case study: Technical Due Diligence for BESS project: 17.75MW / 35.5MWh (FR) 

Battery energy storage contener

Tales of BESS #10 – Case study: Technical Due Diligence on two Greek BESS projects: Totaling 100MW / 200MWh (GRC) 

Solar farm with solar panels with grass

Safety Concerns in Single-Axis Tracker PV Plants: Risks and Mitigation Strategies

battery energy storage system with solar panels and wind turbines behind

Tales of BESS #9 – Case study: Technical Due Diligence on two Greek BESS projects: Totaling 200MW / 400MWh (GRC)

Resources and insights Tales of BESS #7 – Case Study: SOC discrepancy : 32MW / 32MWh (UK)